Apartment conversions go mainstream as the rental housing industry searches for accessibility and affordability.
Adaptive reuse carries far more uncertainty than ground-up construction. In a conversion, teams don’t know what’s behind walls or above ceilings until demolition begins. Hidden steel, floor openings and outdated HVAC systems can quickly reshape a plan, making rigorous preconstruction investigation essential.
But that’s not stopping anyone from creating more much-needed rental housing communities.
As of 2025, the adaptive reuse sector experienced remarkable growth, with office-to-apartment conversions surging from 23,100 in 2022 to an estimated 70,700, according to RentCafe.
These conversions now account for nearly 42% of all adaptive reuse projects, up from 38% last year. This surge underscores the growing recognition of adaptive reuse as a sustainable and efficient solution to urban housing challenges.
To control that risk, contractors front-load coordination. In Chicago, for example, McHugh Construction is converting an Art Deco office tower at 65 E. Wacker Place into 252 apartments for Mavrek Development, with Cross Street leading leasing.
Before coring or routing new systems, the team spent months mapping beams and existing conditions. Through modeling, field surveys and selective demolition, the project is virtually built before crews mobilize, minimizing costly surprises, according to Michael Sinickas, Project Manager for McHugh Construction.
“Mechanical, electrical and plumbing (MEP) coordination is especially demanding, since office buildings weren’t designed for stacked kitchens and baths,” Sinickas said. “New plumbing, HVAC, fire protection and electrical systems must be precisely threaded through the structure.
“Execution hinges on early structural mapping, strategic mechanical, electrical, plumbing planning and tight sequencing. Once construction starts, trades move from floor to floor, and a single delay can trigger a domino effect. That’s why so much effort goes into coordination before the first wall is framed.”
Every floor is uniquely different, said My-Nga Lam, Principal at LJC Design & Engineering.
“Even though residential units are designed to stack vertically on ‘typical’ floors, there are often unique conditions that create distinct unit plans, particularly for units adjacent to cores and stairwells,” she said. “We crawl through spaces on every floor to evaluate such conditions and document them accurately to minimize surprises during construction.
David McCullough, PLA, ASLA, Principal at McCullough Landscape Architecture, said unknown existing construction materials—such as asbestos, lead paint or contaminated soil—can introduce significant remediation costs and delays if discovered after acquisition.
He said that regulatory and community considerations are equally important.
“Developers must assess the local jurisdiction’s and governing agencies’ receptivity to redevelopment, as well as whether zoning or building ordinances may conflict with the intended conversion,” according to McCullough. “In some cases, obtaining variances or navigating regulations can significantly affect timelines and costs.”
Finally, the broader neighborhood context matters: Community sentiment toward development or change can influence the entitlement process and ultimately determine whether a project moves forward without resistance.
Therefore, early due diligence and local engagement can also pay dividends, McCullough said.
“Conducting thorough upfront research, working with experienced local professionals and spending time in the community before making legal commitments can provide critical insight into regulatory expectations, approval processes and potential community concerns,” he said. “This early groundwork helps developers anticipate obstacles and build relationships that can simplify entitlements and approvals.”
Neighbors often feel a strong connection to existing buildings, especially when demolition is involved, and zoning for a new use is not always in place, said Nick Walsh, Vice President of Development at The NRP Group.
“In some cases, preservation requirements can limit the ability to demolish or significantly alter an existing structure,” Walsh said.
“Any time you are dealing with a public entity, there will be lots of regulatory and legal hoops to jump through. For example, on our Anita Coy project in Austin, we had to research the Texas Education Code and work with the Board of Trustees to ensure we complied with all requirements. Having the right team of advisors, lawyers and financial partners helps to get the job done.”
To help move development forward, a Public Facility Corporation was formed. “That was a significant hurdle, but by working closely with the district and educating decision makers, we were able to move the project forward,” said Walsh.
You Can’t ‘Wish Away’ Regulatory Hoops
Alex Panici, Vice President, Skender Construction, said you can’t “wish away” regulatory hoops such as change of use (COU) issues, code upgrades and environmental concerns.
“We front-load due diligence, bring in the right specialists early and work closely with local authorities,” he said. “The trick is to align milestones and public messaging with when approvals are truly in hand, not when everyone wishes they were.”
Panici said muddying the process can be unforeseen conditions in old buildings, pressure to hit aggressive lease dates and a belief that conversions should be cheaper than they actually are.
“We deal with that by building real contingency into cost and schedule and being brutally honest about what the building will and won’t allow,” he said. “Successful conversion work is really about managing uncertainty well.”
He said conversions “look glamorous” in headlines, but they’re hard, messy projects that demand realistic expectations and a very aligned team.
“When owners, designers, contractors and [residents] all accept there will be surprises—and commit to working through them together—that’s when these projects really succeed and create long-term value,” Panici said.
Redevelopment Addresses Affordable Housing Needs
The glut of outdated suburban office parks in markets such as Boston presents a key opportunity to address critical housing needs, said Peter Mahoney, EVP of Development for John M. Corcoran & Co.
“We continue to evaluate opportunities in underutilized office parks, although most of what we’ve looked at has not been zoned for multifamily,” he said. “We are also seeing a number of them going to office owners who think they can reposition them in some way, with maybe the possibility of conversion to multifamily as an upside future alternative because the demand remains strong.”
Elsewhere, The NRP Group, in partnership with the Austin Independent School District (AISD), has broken ground on the aforementioned landmark school-to-housing redevelopment in East Austin. The project will transform the former Anita Ferrales Coy school site into a 675-unit, mixed-income community with the first 341 residences already under construction and a second phase of 334 apartment homes expected to begin this year. The lease-up of the first units is expected to begin in the fall of next year.
Designed to address Austin’s growing affordability challenges, the development will prioritize housing for cost-burdened residents and essential workers, including AISD teachers and staff, while repurposing underutilized public land through a public-private partnership (P3) model.
Deep Floor Plates, Deep Trouble
Every conversion project has its own challenges, and it can take a lot of creativity to solve them, said Mike Krych, Senior Design Leader and Development Managing Partner, BKV Group.
“In some cases, we find that you can’t [convert a building],” Krych said. “There are certain characteristics we know a project needs to be marketable – and profitable – for residential, which also happen to be common obstacles in a conversion, so we focus on identifying them from the start.”
For example, many commercial-to-residential conversions involve early-1900s warehouse buildings with very deep floor plates, making it difficult to bring in the amount of light needed for residential units.
“We look at ways to carve out light wells and atriums in the center of these deep buildings and surround them with units to increase density and bring in daylight, but from the outside, it looks like nothing changed,” Krych said.
Another typical challenge is accommodating parking on a site that doesn’t have any, especially if the column spacing is too narrow to allow parking in the basement or lower levels.
“We’ve come up with solutions that remove a column supporting seven or 10 floors above it and transfer that load to another column, which creates enough space for a car to make a turn and park in the basement,” Krych said.
For Duffey Lofts, which revitalized the Duffey Paper Company’s site in Minneapolis, a thin structure was used to insert a four-story garage within a warehouse on the property, creating a parking solution that works within the confines of the existing building.
“The fact that the building rarely matches the provided drawings is another challenge, if a complete set of drawings even exists in the first place,” he said.
What can be found are hidden structural elements and modifications made over the decades, uncharted utilities and deteriorating systems, which means that field verification is practically a requirement.
The Beauty of Simple Rectangular Shapes
One green light when converting an office building, Lam said, is a project in a high-demand area with several adaptive reuse incentives available, including expedited approvals.
“Buildings in a neighborhood that has a high walkability score with access to public transportation are also favorable,” she said.
“Buildings with a simple rectangular shape and structural bays are ideal for laying out residential units,” Lam said. “Office buildings typically have higher ceiling heights and large windows that make the building more attractive and unique for residential.”
Historical buildings (those with “landmark” designations) can be attractive opportunities due to their inherent architectural character and ornate exterior and interior details that cannot be replicated today, Lam said.
“But if the building is not in good condition, the cost to restore and preserve details can drive up construction costs, compared to a full building replacement.
Not all office buildings have terraces or parking, Lam said, whereas new apartment development accounts for that – if not, it requires it.
“Sometimes it can be very challenging and cost-prohibitive to integrate this program within the building in the adaptive reuse redesign process,” Lam said.
In one case, the 208 S. LaSalle project is on a designated landmark registry, and its façade and main lobby must be preserved.
“Any modifications or additions that would significantly affect those areas require review and approval by the city’s preservation board,” Lam explained. “The project will include adding a new canopy above the main entrance and replacing all windows. We have selected windows that resemble the original. For the canopy, the design is more traditional, and the use of metal and glass complements the historic façade.
“Although it is sometimes challenging to accommodate these requirements, we can typically get very creative to meet these planning standards,” Lam said.
McCullough said certain regulatory considerations are important depending on the location.
For example, in California, fire safety and seismic standards can pose significant design and engineering challenges and often affect project costs and insurability. In many jurisdictions, stormwater management requirements must also be addressed, as local regulations increasingly require projects to manage runoff and environmental impacts.
“Understanding and planning for these factors early in the process allows developers to incorporate solutions into the project design rather than encountering costly surprises later,” he said.
‘Meaningful’ Uptick in ReDev Loans
There’s been a meaningful uptick in developers seeking financing for office-to-residential conversions, said Ben Jacobson, a Partner with Forman Capital.
“As land becomes scarcer and ground-up development faces cost and zoning hurdles, adaptive reuse is emerging as a practical solution. These projects not only unlock value in underperforming office assets but also help meet ongoing residential demand.”
The primary driver is the structural shift in office demand following COVID: Companies have significantly reduced office footprints; larger office spaces (20,000 to 40,000 square feet) are now harder to lease.
Many office owners are also facing loan recasts at much higher interest rates, with prior loans at 3%–4% resetting to 7%–9% or higher. That, combined with lower occupancy, means many owners cannot service the new payments.
As a result, some buildings are being sold or repositioned at distressed pricing, making them attractive for redevelopment and adaptive reuse.
While underwriting fundamentals remain the same, conversion loans require stronger sponsor credibility and well-supported pro forma projections because lenders are financing future performance (looking out three to six years) rather than an already stabilized asset.
Adaptive Reuse Smarter than Ground-Up Construction
Despite the constraints that can accompany conversion projects, adaptive reuse is often a smarter and more widely supported approach than starting from the ground up, McCullough said.
Communities frequently view conversions more favorably than new construction, since reusing existing buildings can feel like preservation and reinvestment rather than displacement. When done thoughtfully, these projects are seen as strengthening the neighborhood, not reshaping it.
Conversion also offers clear sustainability benefits. Reusing existing materials and structural elements reduces the need for new raw resources and limits construction waste, making adaptive reuse one of the most practical ways to support sustainable building practices.
In many cases, regulatory agencies also view renovations as less complex than ground-up development, which can make approvals more straightforward and sometimes faster, helping projects move from concept to completion more efficiently.
Unique Circumstances for Redevelopment
The 208 S. LaSalle building was designed by Daniel Burnham and built in 1914. Construction in that era differed greatly from today; steel structural systems generally had heavier reinforcement and could carry significantly more load than was needed.
Due to its structural strength, particularly at the top of the building, the addition of a new rooftop swimming pool and a potential new ballroom that can accommodate events for up to 300 people is feasible.
A developer in Southern California had a property on a hillside in San Diego, which the local agency considered a “high fire severity” zone. The developer had received sign-off from almost all departments for the building permits. However, their project was in the middle of the review process when the Palisades fire occurred in the Los Angeles area. Because of substantial property loss from this fire, the fire department took a closer look at the plans and responded with a new set of comments that made the project virtually unbuildable.
McCullough Landscape Architecture’s office reviewed the comments, identified the “intent” of the comments, and then worked with the local fire marshal to develop “alternative compliance” measures deemed adequate by the reviewer. The project was therefore approved.
The point is that, regardless of the stringency of agencies’ comments or building codes, understanding “intent” is critical to providing flexible solutions to problems that may arise.
“One of the crazier dynamics in this space is how a building can sit on the shelf for years because the math doesn’t work—and then, once the right [tenent] or market shift shows up, you’re suddenly racing to untangle a century of structural, environmental and code issues,” according to Alex Panici, Vice President, Skender Construction.
“On paper, it looks like a simple ‘flip the use’ exercise; in reality, you’re reconciling decades of history with today’s performance and schedule expectations.”
Paul Bergeron is a freelance writer.